Monday, 22 October 2012

What a week

Well we have been told house should be finished in 5 weeks, we will see.
We have seen the tiles nearly all complete as well as paint starting this week and kitchen next week.
We were upset when other double stories that started after us are ready for drive ways and hand over but are excited and hopeful that ours will be full steam ahead.
Here are pics of our tiles

Monday, 15 October 2012

Sorry to bombard you with more posts

We have had a lot of work done today, a front door, tiles cleaned up, sliding doors put in, a laundry door and skirting started to go up. Apparently it should be finished by the end of the end.
We had a walk through with our builder and have had our concerns addresses. Hoping to see them corrected before paint starts.

Saturday, 13 October 2012

Tiles have started

Our main floor has been started and finished in two days. We love the colour and can't wait for everything to come together.
Here are some pics below of kitchen, family room, laundry and facing the entry.

Wednesday, 10 October 2012

We have garage doors

We were told we would have garage doors today, and we are happy to report they look fantastic!
Tiles arrived yesterday and are said to be starting tomorrow.
The doors and skirtings that were delivered two weeks ago are still on the floor and the painting still hasn't been done.
Next week shall be exciting indeed

Monday, 8 October 2012

Not much of an update

So three weeks later and not much else has been done. In a month we have seen gyprocking, stairs, cornices, waterproofing and external plumbing.
The doors and skirting has sat on the floor for over a week and we were told they would be done for paint and tiles to start mid this week.
Not sure whats going on or why this is happening, just over it all really and wish we could just get it over and done with.
So a pic of each bathroom which is waiting for tiles